If Your Generator Has Never Run at Full Load... You Don't Know If It Will Perform When You Need It Most.
Load bank testing applies a controlled electrical load to a generator to simulate real-world operating conditions. It forces the generator to produce and sustain rated power, revealing any mechanical or electrical issues that do not appear at partial or no-load operation.
Stag supplies the generators and power distribution infrastructure required to conduct load bank testing wherever your facility or project is located. We work alongside your load bank provider or testing contractor.
How a Load Bank Test Is Conducted?
A complete test steps up in increments so performance at each level is verified before progressing. A full NFPA 110-compliant annual test requires a minimum of two continuous hours at 100% rated capacity.
Stages 1 & 2
25% – 50%
Warm-up and mid-load check. Confirms startup under load, establishes baseline operating temperature, and verifies voltage and frequency stability at half-load.
Stage 3
75% Load
High-load run. Engine response, cooling system performance, and fuel delivery are all confirmed under stress conditions before advancing to full load.
Full Compliance Test
100% Load
Full-load for a minimum of 2 continuous hours. Required for NFPA 110 annual compliance, new generator commissioning, and wet stacking correction.
NFPA 110 also requires monthly tests at 30% load for a minimum of 30 minutes. Facilities that only conduct monthly partial-load tests are at risk of wet stacking and undetected performance degradation.
The Cost of Skipping Load Bank Testing
What Happens When a Generator Has Never Been Tested Under Full Load
| Issue | Potential Cost |
|---|---|
| Wet Stacking Repair | Up to $2K–$8K |
| Hidden Alternator Fault | Up to $4K–$20K |
| Generator Failure During Outage | $25K–$100K+ |
Monthly Testing vs. Annual Full-Load Testing
Not Sure What Testing Your Facility Requires?
NFPA 110 requires both monthly and annual testing. Both are mandatory, but they serve different purposes and require different equipment setups.
Annual Full-Load Test
NFPA 110 Compliance
2 continuous hours at 100% nameplate kW. Pre-test inspection, load data, and post-test sign-off required by code.
Burns Off Wet Stacking
The only way to burn off accumulated deposits from extended light-load operation. Restores full rated output and normal exhaust characteristics.
What Stag Supplies
Generator, iLine panel, distribution cables, and fuel for extended runs. Your load bank provider brings the load bank.
Monthly Partial-Load Test
30 Minutes at 30% Load
Minimum monthly requirement under NFPA 110. Log date, load level, duration, and any faults. Confirms startup and basic operation.
Wet Stacking Risk
Running exclusively at 30% load over time causes unburned fuel to accumulate in the exhaust system. Annual full-load test corrects this.
Who It Applies To
Hospitals, data centers, water utilities, emergency services, and any facility with a required standby system under NFPA 99, 101, or local code.
Rent a Generator for Load Bank Testing
Stag provides the generator and distribution infrastructure for your load bank test setup. We work alongside your testing contractor and can have equipment on site in as little as one day.
20kW
Smallest in fleet
2,000kW
Largest in fleet
Same-day
Dispatch available